| Task Description | Resources | Timeframe | Task Status |
|---|---|---|---|
| Cards and software | |||
| Order Nortel 10G EPL prototype cards | CANARIE, SURFnet | Completed | |
| Ship 10G EPL prototype cards | Nortel | Was scheduled for week of 17 July | 18 Sep, 2006 - the First 10G EPL card has been delivered by Robert to CANARIE office and the Second card will be shipped to BCnet by tomorrow and should be in BCnet by Wednesday. |
| Verify availability of Alcatel 10G EPL card | DANTE | Completed. Is in service in GEANT2. Frankfurt interface ideal end-point. | |
| Verify Nortel support for pluggable DWDM optics | CANARIE, Nortel | Completed. Nortel will disable software verification of XFPs. TRIUMF will provide a 1500.12nm XFP | |
| Deliver OME Release3.0 software load | Nortel | Completed. Nortel has delivered the release 3.0 | |
| Install OME Release3.0 software load | CANARIE | Complete. Installation was completed in the week of Oct 3. Edmonton and UofV? OME are upgraded first, and the rest of them are done in two days later | |
| Test plan | |||
| Draft Carleton U to Lab10 Test Plan | CANARIE, Carleton U, Nortel | 26 Oct 2006 | Carleton-Nortel |
| Draft Carleton U to TRIUMF Test Plan | Carleton U, Nortel | 30 Oct 2006 | Carleton-TRIUMF |
| Draft TRIUMF to CERN Test Plan | TRIUMF, CERN | ?? Nov 2006 | TRIUMF-CERN |
| Draft Nortel-Alcatel 10GE EPL interoperability Test Plan | CANARIE, DANTE, Nortel, SURFnet | René and Bart to send draft to DANTE and SURFnet for review | |
| LightPath? engineering and provisioning | |||
| Engineer and provision Carleton U to Lab10 LightPath? | CANARIE, CarletonU?, Nortel | 31 July 2006 | CANARIE to complete detailed design |
| Engineer and provision Carleton U to TRIUMF LightPath? | CANARIE, Carelton U, TRIUMF | 31 July 2006 | CANARIE to complete detailed design |
| Engineer and provision GEANT2 to SURFnet LightPath? | DANTE, SURFnet | DANTE and SURFnet to complete detailed design. | |
| Test equipment | |||
| Obtain 10GE test equipment for throughput testing from Carelton U | Carleton U, Nortel | Nortel will loan test gear to Carleton U | |
| Obtain 10GE test equipment for throughput testing from GEANT2 end-point to SURFnet | DANTE, SURFnet | DANTE should be able to get a loaner from Alcatel | |
| Testing | |||
| Execute Carleton U to Lab10 Test Plan | Carleton U, Nortel | mid August 2006 | - 27 Oct, 2006: Tests were performed at Carleton U. Bart has brought in a 10GE testset for use as an end device for testing. We ran into a bit of problem with the 10GE EPL card. For some reasons, it locked up in the middle of testing. First we thought it was problems on the testset due to the fact that Bart was quite famillar with the testset. After a few hours testing, we decided to stop and came back some other time so Bart can get familiar with the testset. - 10 Nov 2006 - We went through the tests we did couple weeks ago trying to reproduce the problems we ran into before. We did identfiy the lockup problem with the 10GE EPL card. The problem is the incrementing packet/frame size that test set generated which produced the repeatable lockup of the EPL card. The problem is reproduceable every time with the same packets pattern. Bart will bring this up with the engineering to look into this. Other than the problem, CCAT and VCAT is working properly. sts3c-16v and sts3c-32v VCAT circuits were tested. |
| Execute Carleton U to TRIUMF Test Plan | Carelton U, TRIUMF | 31 August 2006 | - 9 Nov 2006: David tried to install the 10GE EPL in Vancouver OME, he noticed that the daugther broad on the card wasn't secured so he has secured the card with one screw. The card power up fine but we would bring the card in service. The system doesn't recognize the card at all. I have sent an email to Bart and Robert and asked them for their advices. - 17 Nov 2006: Nortel support has logged in the the system, they has confirmed that the card is dead. So we need another card to support the TRIUMF 5G lightpath that should be online very soon. Robert is helpping to locate other proto-card for temporary use. 21 Nov 2006 - Robert got back to us saying that there will be a delay for the three new cards, they has been pulled back due to problems found with card components, they will not be ready until Feb, 2007. We can delay the deployment of the 5G circuit so I decided to take the 10GE EPL card in Ottawa to be used in Vancouver. We'll try to get another proto-card from Robert in Ottawa |
| Execute Nortel-Alcatel 10GE EPL interoperability Test Plan | DANTE, SURFnet | 31 August 2006 | |
If the start/end dates for main activities are known, you could display everything as follows:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||
You see...
-- HerveGuy - 18 Jul 2006